Skip to content

Electric Power Service (EPS) Business Model

Overview

The EPS-Electric-Power-Service (PG) model represents an off-grid hybrid energy system combining solar PV, battery storage, and backup generation (genset/grid) to supply electricity to the e-mobility ecosystem. This model is optimized for high PV-to-Battery ratios (2.0-6.0) to maximize direct solar-to-load supply and minimize battery cycling costs.

Business Context

Central Question: "How can we minimize energy costs while ensuring 24/7 power availability?"

Critical Modeling Methodology: Integer Unit Constraints

Physical Architecture

EPS-Electric-Power-Service Unit = 120kW Solar + 261kWh Battery - 1 Unit = 120 kWp solar + 261 kWh BESS + 100 kW inverter (fixed physical constraint) - Modular Expansion: Capacity grows in discrete base unit increments - Cannot deploy partial units: 1, 2, 3... units only (not 1.3 or 2.7 units)

Two-Layer Economic Model

The model explicitly separates installed capacity (integer-constrained) from actual usage (demand-driven) to capture the economic impact of modular infrastructure:

Infrastructure Layer (Integer-Constrained): - Installed units: EPS_SCALE_FACTOR (integer: 1, 2, 3...) - Installed solar: EPS_SCALE_FACTOR × 120 kWp - Installed battery: EPS_SCALE_FACTOR × 261 kWh - Total CapEx: Based on installed units - Fixed OpEx: Based on installed capacity (maintenance, land, security)

Operational Layer (Demand-Driven): - Active energy demand: From demand-supply model (ds_total_energy_demand) - Utilization rate: ds_total_energy_demand / (EPS_SCALE_FACTOR × 541 kWh/day) - Revenue: Based on actual energy delivered - Variable OpEx: Based on usage (fuel, grid purchases)

Economic Impact of Integer Constraints

Example: Test Case A - Demand: 714 kWh/day energy needed - Supply: Must install 2 units = 2 × 541 kWh/day = 1,082 kWh/day capacity - Utilization: 714/1,082 = 66% - Oversizing penalty: 368 kWh/day unused capacity, diluted fixed costs

Example: If Demand = 600 kWh/day - Demand: 600 kWh/day needed - Supply: Must install 2 units = 1,082 kWh/day (cannot deploy 1.1 units) - Utilization: 600/1,082 = 55% - Oversizing penalty: Larger capacity underutilization, higher LCOE

Key Principle: Off-grid power infrastructure can only expand in discrete modular units (120kW/261kWh base units). When demand doesn't align with unit capacity, you're forced to overbuild, reducing utilization and increasing levelized cost of energy.

Terminology

  • Base Unit: 120kW/261kWh physical system (indivisible)
  • Scale Factor: Integer multiplier (number of units deployed)
  • Installed Capacity: Total generation capacity (scale factor × 541 kWh/day)
  • Active Demand: Actual energy consumed (from demand model)
  • Utilization Rate: Active / Installed (100% = optimal, <100% = oversizing penalty)
  • LCOE Impact: Lower utilization → higher fixed cost per kWh → higher LCOE

Key Strategy: - Oversize solar PV relative to battery capacity - Maximize daytime direct-to-load solar supply - Use batteries for night-time load only - Minimize expensive diesel/grid backup usage

Model Parameters

Base Unit Configuration

Parameter Symbol Value Unit
Base solar capacity EPS_SOLAR_CAPACITY_BASE 120 kWp
Base battery capacity EPS_BATTERY_CAPACITY_BASE 261 kWh
Base inverter rating EPS_INVERTER_RATING_BASE 100 kW
Number of units EPS_NUM_UNITS 1 units
Base unit cost EPS_BESS_BASE_COST 156,600 USD
Installation rate EPS_BESS_INSTALL_RATE 10% ratio

Cost Parameters

Parameter Symbol Value Unit
PV module FOB cost EPS_PV_COST_FOB 0.30 USD/Wp
PV installation cost EPS_PV_INSTALL_COST 0.20 USD/Wp
Genset capacity EPS_GENSET_RATING 50 kW
Genset CapEx EPS_GENSET_CAPEX 500 USD/kW
Diesel fuel price EPS_DIESEL_PRICE 1.20 USD/L
Grid electricity cost EPS_GRID_COST 0.32 USD/kWh
Electricity selling price EPS_ELEC_PRICE 0.32 USD/kWh
Annual maintenance rate EPS_MAINT_RATE 5% ratio/year

Technical Parameters

Parameter Symbol Value Unit Description
Peak Sun Hours (PSH) EPS_PEAK_SUN_HOURS 5.5 hours/day Location-specific solar resource (Togo: 5-6 hrs, NASA data)
System Derating Factor EPS_SYSTEM_DERATE 0.82 ratio Combined losses: temperature, wiring, MPPT, dust (0.80-0.85)
Inverter efficiency EPS_INVERTER_EFFICIENCY 95% ratio DC-to-AC conversion efficiency
Battery round-trip efficiency EPS_BATTERY_EFFICIENCY 90% ratio Charge-discharge efficiency (10% loss)
Genset fuel efficiency EPS_GENSET_EFFICIENCY 0.25 L/kWh Diesel consumption at rated load
Daytime demand ratio EPS_DAY_DEMAND_RATIO 60% ratio Portion of demand during solar hours

Asset Lifecycle

Parameter Symbol Value Unit
Solar PV lifespan EPS_SOLAR_LIFE 9,125 days (25 years)
Battery cycle life EPS_BATTERY_CYCLE_LIFE 6,000 cycles
Electrical equipment life EPS_ELECTRICAL_LIFE 3,650 days (10 years)

Financial Calculations

Key Solar Ratios (Industry Standard)

Metric Formula Unit Description
PV-to-Battery Ratio (PB Ratio) eps_solar_capacity / eps_battery_capacity kWp/kWh PRIMARY OVES METRIC: 2.0-6.0 for e-mobility
Array-to-Load Ratio (ALR) eps_daily_production_potential / ds_total_energy_demand ratio Solar generation / daily load (1.2-2.5 typical)
PV Oversize Ratio eps_solar_capacity / eps_inverter_rating ratio PV array / MPPT rating (1.2-2.0 typical)
Daytime Solar Fraction eps_solar_to_load / ds_total_energy_demand ratio Load served directly by solar (key economic metric)

Energy Flow Calculations

Daily Production:

eps_daily_production_potential = eps_solar_capacity × EPS_PEAK_SUN_HOURS × EPS_SYSTEM_DERATE

Solar Energy Distribution:

eps_solar_to_load = MIN(eps_daily_production_potential, eps_day_demand)
eps_solar_excess = MAX(0, eps_daily_production_potential - eps_day_demand)
eps_solar_to_battery = MIN(eps_solar_excess, eps_battery_capacity / EPS_BATTERY_EFFICIENCY)

Battery Operations:

eps_battery_stored = eps_solar_to_battery × EPS_BATTERY_EFFICIENCY
eps_battery_discharged = MIN(eps_battery_stored × EPS_BATTERY_EFFICIENCY, eps_night_demand)
eps_battery_cycles_day = eps_battery_stored / eps_battery_capacity

Backup Generation:

eps_shortfall = MAX(0, eps_night_demand - eps_battery_discharged)
eps_grid_purchase = eps_shortfall × 0.3
eps_genset_output = eps_shortfall × 0.7
eps_genset_fuel_consumed = eps_genset_output × EPS_GENSET_EFFICIENCY

Capital Expenditures

eps_pv_capex_total = eps_solar_capacity × 1000 × (EPS_PV_COST_FOB + EPS_PV_INSTALL_COST)
eps_bess_capex_total = EPS_BESS_BASE_COST × EPS_NUM_UNITS × (1 + EPS_BESS_INSTALL_RATE)
eps_genset_capex_total = EPS_GENSET_RATING × EPS_GENSET_CAPEX
eps_total_capex = eps_pv_capex_total + eps_bess_capex_total + eps_genset_capex_total

Operating Costs

eps_daily_fuel_cost = eps_genset_fuel_consumed × EPS_DIESEL_PRICE
eps_daily_grid_cost = eps_grid_purchase × EPS_GRID_COST
eps_daily_maint_cost = (eps_total_capex × EPS_MAINT_RATE) / 365
eps_daily_opex = eps_daily_fuel_cost + eps_daily_grid_cost + eps_daily_maint_cost

Depreciation

eps_pv_daily_depreciation = eps_pv_capex_total / EPS_SOLAR_LIFE
eps_bess_cycle_depreciation = eps_bess_capex_total / EPS_BATTERY_CYCLE_LIFE
eps_bess_daily_depreciation = eps_bess_cycle_depreciation × eps_battery_cycles_day
eps_genset_daily_depreciation = eps_genset_capex_total / EPS_ELECTRICAL_LIFE
eps_total_daily_depreciation = eps_pv_daily_depreciation + eps_bess_daily_depreciation + eps_genset_daily_depreciation

Financial Metrics

eps_daily_total_cost = eps_daily_opex + eps_total_daily_depreciation
eps_annual_production = eps_total_supply × 365
eps_lcoe = eps_daily_total_cost / eps_total_supply
eps_daily_revenue = eps_total_supply × EPS_ELEC_PRICE
eps_daily_profit = eps_daily_revenue - eps_daily_total_cost

Output Metrics

Key Performance Indicators

KPI Reference Unit
Total Capital Expenditure eps_total_capex USD
Daily Energy Supply eps_total_supply kWh/day
Annual Production eps_annual_production kWh/year
Daytime Solar Fraction eps_daytime_solar_fraction × 100 %
Battery Cycles Per Day eps_battery_cycles_day cycles/day
Genset Runtime eps_genset_runtime hours/day
Levelized Cost of Energy (LCOE) eps_lcoe USD/kWh
Daily Revenue eps_daily_revenue USD/day
Daily OpEx eps_daily_opex USD/day
Daily Depreciation eps_total_daily_depreciation USD/day
Daily Profit eps_daily_profit USD/day
Profit Margin (eps_daily_profit / eps_daily_revenue) × 100 %
Payback Period eps_total_capex / eps_daily_profit days
Array-to-Load Ratio (ALR) eps_array_to_load_ratio ratio
PV-to-Battery Ratio (PB Ratio) eps_pv_to_battery_ratio kWp/kWh
PV Oversize Ratio eps_pv_oversize_ratio ratio

Interdependencies with Other Models

Dependencies FROM Other Models

Source Model Data Required Impact
Demand-Supply ds_total_energy_demand Determines required generation capacity
Demand-Supply DS_PEAK_SUN_HOURS Reference for solar resource planning
Demand-Supply DS_INVERTER_EFFICIENCY Reference for system sizing

Dependencies TO Other Models

Target Model Data Provided Impact
Demand-Supply Electricity pricing (EPS_ELEC_PRICE) Energy cost structure for ecosystem
SNS-Swap-Network-Service Power availability Station operations planning

Off-Grid Design Strategy

Why High PV-to-Battery Ratios?

  1. Morning/Evening Extension: Oversized PV starts generating earlier and continues later
  2. Direct-to-Load Supply: Daytime loads bypass battery (no cycling cost)
  3. Battery Investment Reduction: Smaller batteries + more panels = lower total cost
  4. Operational Resilience: Multiple energy sources reduce single-point failure risk

Trade-offs: - Higher initial PV CapEx - Some mid-day solar may exceed system absorption capacity - But: Lower battery replacement costs + reduced diesel/grid dependence

Reference

For detailed off-grid solar terminology, sizing methodology, and industry best practices, see:

📘 Off-Grid Solar Primer

Key concepts covered: - Peak Sun Hours (PSH) and irradiance - PV-to-Battery Ratio (PB Ratio) as primary design metric - Array-to-Load Ratio (ALR) and system sizing - Daytime Solar Fraction and economic optimization - Industry-standard terminology and typical ranges

Version History

Version Date Changes Author
0.2 2025-11-16 Added full calculations with industry-standard solar metrics OVES Team
0.1 2025-11-02 Placeholder created OVES Team